A project manager schedules meetings for many different reasons. Status review meetings are typically held:
a) To provide all stakeholders with critical project information
b) To exchange information about the project between project team members
c) To update departmental staff of project status
d) Only when there is a need for a workaround
Answer: B – Generally, project status meetings provide the project team and those stakeholders directly involved in project activities with up-to-date information about the project. Other stakeholders and higher-level managers may receive information through formal reports or specifically scheduled meetings. Workarounds are temporary responses to an unplanned situation and generally require immediate action.